10 men, 30tonne of scaffold, 2 trucks, 2 supervisors and 2 utes.
Replacement of wharf gangway then blasting and painting structural steel.
This was a 5 week shutdown that was completed on time, within budget and incident free. A total of 6 large scaffolds were built including a hung scaffold which was 26m long and 2.1m wide with a cantilevered section of another 2.4m wide . All drawings and planning were communicated and supplied to the client throughout the entirety of the job.